NUVIA is implementing fire barrier seals in openings in compliance with the highest standards at the new EPR in Flamanville.
Start date: April 2016
End date: March 2019
The main challenge of the project is to carry out works on-time, safely and in accordance with the specifications and qualifications. NUVIA Structure and NUVIA Protection created a joint venture to carry out the project.
Key details
Challenges
- Quality: On-site implementation in compliance with the qualifications
- Safety: 0 accident
- Delivery Programme: Works completion planned prior to fuel arrival (before the end of 2018)
Scope
- One year was necessary for studies: requirements, analysis and definition of solutions
- Product qualifications: tests performed in NUVIA’s fire rated Lab (Pierrelatte, France). Total duration: 9 months
- On-site works: sealing of 3000 openings in less than 18 months